Solution ID: prim1662 |
When copying a project that does not have the Copy Activity Option checked for Resources & Role Assignments, the resources and roles appear in newly copied project. |
Status: Reviewed |
Version(s): 3.x |
Fact: | Copy/Paste |
Problem: | When copying a project that does not have the Copy Activity Option checked for Resources & Role Assignments, the resources and roles appear in newly copied project. |
Fix: | This known problem in Project Manager has been corrected in version 4.0. Workaround: [Options] |